Thursday, May 22, 2008

Finishing the Frame


The last rafter is in place. Now it will be time to put the tongue and groove ceiling boards to support the roof panels

Starting the Rafters







Framework starting to take shape


The First Post

Every journey begins with the first step. Erecting a timberframe starts with erecting the first post. Scott Greve with the ceremonial first post.

Tedious Oiling Process

We had the weekend to get a head start and try to keep up with the framers. Cans of land ark in the foreground.

Time to Oil the Timbers

All 536 pieces of timbers had to be manually oiled by hand by my wife and I - with Land Ark oil which is proprietary combination of linseed, tung oil and citrus which both cleans and oils the timbers. All ends had to be brushed with beeswax.

Unloading and Staging Timbers



Next step is to unload and stage ready for oiling and installation.

Arrival of the Timbers


The entire frame work on one truck. Scott Greve's crew unloaded it with the All-Terrain forklift I rented. Tam and Wes were the ones unloading.

Basement Construction - 5



Now it is time to check how good a job Scott did in constructing the deck. The floor needs to be level to within +/- .25 inch over the entire length. My level says he did better than that. The floor is level to within +/- 0.125 inch over the 80 foot length of the main deck. Nice job Scott Greve.

Basement Construction 4 - Boards for Main Deck


The main deck is Advantech T&G Flooring.

Basement Construction - 3

Joists are now in place for the deck

Basement Construction - 2


It took many days before the basic framework started taking shape.

Basement Construction - 1

The next crew to arrive is that of Scott Greve the framer. He will construct the basement, the post and beam structure and the garage. Big piles of lumber arrived as the crew stated their layout work.